Starting this Monday night, February 11 thru February 22 on weeknights, the Bronx River Parkway's southbound lanes will be closed from Crane Road to Christie Place. As I blogged last May 10, the Crane Bridge is being replaced by the county in a 39 million dollar project. The existing bridge, build in 1924, was deteriorating and needed to be replaced or repaired.  
On the above dates, from 8:00 pm to 6:00 am, a large crane will be on the parkway in order to install 25 foot high concrete forms for the new bridge.



In March, the same closures will be repeated in order to remove the concrete forms.

Sometime in April or May, 12 more beams will be installed over the Metro-North Railroad tracks. The closures for this work will be forth coming.

To find out more about the project you can visit:

http://publicworks.westchestergov.com/crane-road-bridge